Project Experience

Below is a list of jobs that we have or are currently working on
NO SCHEDULE (START DATE – END
DATE)
CLIENT MAIN CONTRACTOR PROJECT NAME LOCATION SCOPE OF WORK CONTRACT NO. CONTRACT DATE  
1May 22, 2004 – December 20, 2004 VICO Indonesia PT. Perdana Karya VLP Compression Nilam, Samarinda – East
Kalimantan
Electrical & Instrument 048.Plan/PK-PKU/Smd-V/04 May 22, 2004
2July 14, 2004 – October 24, 2004 VICO Indonesia PT KELSRI Construction of Samberah S-13 VLP Gas
Compression
Samberah – East Kalimantan Construction, Electrical, Instrument, & Calibration 2004 WO 199 July 09, 2004
3December 23, 2004 – January 23, 2005 VICO Indonesia PT. Perdana Karya Replacement of Orrifice Plate for Badak Well
Surveillance Phase II
Muara Badak – East
Kalimantan
Calibration 193/SPK-BDK/XII/2004 December 20, 2004
4December 23, 2004 – January 23, 2005 VICO Indonesia PT. Perdana Karya Drill Hole Pipe Support & Calibration for
Badak Well Surveillance Phase II
Muara Badak – East
Kalimantan
Calibration 192/SPK-BDK/XII/2004 December 20, 2004
5March 15, 2005 – April 18, 2005 PT. Banpu Indominco PT. SAS Internasional Marine Monitoring System Bontang – East Kalimantan Construction 00371-SUBCONT-INS-009 March 08, 2005
6March 07, 2005 – April 20, 2005 Unocal PT. Perdana Karya CEMS Lawe-Lawe Terminal,
Balikpapan – East Kalimantan
Material Supply, Electrical,
& Instrument
072.Plan/PK-KPU/Smd-III/05 March 17, 2005
7July 09, 2005 – December 20, 2005 VICO Indonesia PT. Perdana Karya VLP Compression Muara Badak – East
.Kalimantan
Electrical & Instrument 075/PK-KPU/Smd-VII/05 July 19, 2005
8August 01, 2005 – August 04, 2005 VICO Indonesia PT. Perdana Karya Telemetry Muara Badak – East
Kalimantan
Calibration 715/SPK/BDK/VIII/2005 August 01, 2005
9August 11, 2005 – September 11, 2005 EMP Kangean Limited PT. Perdana Karya Compressor Dismantling C-8100 & C-8500 Pulau Pagerungan – East Jawa Electrical & Instrument 0102/PK-KPU/Smd-VIII/05 August 18, 2005
10September – October 2005 EMP Kangean Limited PT. Perdana Karya Pagerungan Well Connection Pagerungan Base – East Jawa Electrical & Instrument 0104/PK-KPU/Smd-VIII/05 August 18, 2005
11October 1, 2005EMP Kangean Limited PT. Perdana Karya Compressor Dismantling C-1501, 1502, 1503 Pagerungan Plant, Pagerungan
Base – East Jawa
Electrical & Instrument 0107/PK-KPU/Smd-X/05 October 24, 2005
12September 01, 2005 – June 30, 2006 PT. Badak NGL PT. SAS Internasional HMCS 1000 Improvement Bontang – East Kalimantan Installation Instrument &
Control System
CA-04047 August 26, 2005
13November 07, 2005 – December 31,
2005
PT. Badak NGL PT. SAS Internasional Replacement of Marine Monitoring System at Dock #2 Bontang – East Kalimantan Engineering & Construction C-05039 August 26, 2005
14January 12, 2006 – March 31, 2006 VICO Indonesia PT. Yasa Industri Nusantara Construction of Badak Compressor Restage Muara Badak – East
Kalimantan
Electrical & Instrument 002/05.34608/YIN- KPU/SPB/2006 January 12, 2006
15January 26, 2006 – February 02, 2006 PT. Kaltim Methanol Industri Restroke Control Valve & Rekalibrasi
Transmitter
Bontang – East Kalimantan Calibration E033/PO-KMS/I/2006 January 13, 2006
16March 01, 2006 – March 31, 2006 PT. Syrindo Mono Indonesia PT. Rekayasa Engineering Fuel Oil Blending Facility Cilegon – Banten Installation Steam Tracing
Material
MFO-01-PR-CT-002 March 01, 2006
17April 1, 2006EMP Kangean Limited PT. Perdana Karya Pulling Power Cable Construction Pipeline P. Sepanjang, Pagerungan Base –
East Jawa
Pulling Cable 3 Line x 1.5
km
001/PK-KPU/Smd-IV/06 April 04, 2006
18May 2006 – June 2007 PT. Badak NGL PT. Inti Karya Persada
Tehnik
DCS Centum V Replacement Bontang – East Kalimantan Electrical & Instrument PGV-CD-CR-J-0001 March 24, 2006
19June 1, 2006PT. Indominco Mandiri Pengadaan Barang : Light Meters TM-203 Bontang – East Kalimantan Material Supply A20610600 June 08, 2006
20August 1, 2006PT. Indominco Mandiri Pemindahan Kabel Power Bontang – East Kalimantan Construction, Electrical &
Material Supply
75/P/IMB-KPU/VIII/2006 August 04, 2006
21September 15, 2006 – December 14,
2006
VICO Indonesia/PT.
Promatcom Tepatguna
TCP Retrofit di Nilam (Vico Plant) Muara Badak – East Kalimantan Electrical & Instrument SPK-001/EPC264.KPU/IX- 2006 November 07, 2006
22September 1, 2006PT. Badak NGL/PT. GE
Operations Indonesia
Panel Wiring di SIH pada Proyek Shutdown
Train-E PT. Badak NGL
Bontang – East Kalimantan Manpower Supply
23April 2007 – October 2007 Total E & P Indonesia PT. Perdana Karya 220VAC Power Supply for Telecom Cabinet
and Lightning Protection System
Handil – East Kalimantan Electrical 001/PK-KPU/Total/IV-2007 April 10, 2007
24April 20, 2007 – April 19, 2008 Total E & P Indonesia/PT.
Promatcon Tepatguna
Installation of 6 Desander Units on Handil
Wells Handil Field
Handil – East Kalimantan Instrument 4500004382May 03, 2007
25May 01, 2007 – December 31, 2007 PT. Badak NGL Halon 1301 Replacement for Loading Dock 1
& 2 and Train “E-H” MCR
Bontang – East Kalimantan Engineering, Procurement, & Construction C-06197 May 01, 2007
26June 07, 2007 – June 12, 2007 PT. Megaron Semesta Instrument Commisioning for GDU Unit Samarinda – East Kalimantan Commissioning 8001April 19, 2007
27June – July 2007 PT. Promatcon Tepatguna Total Desander Handil – East Kalimantan Material Supply 4500004362June 26, 2007
28August 16, 2007 – August 15, 2008 PT. Badak NGL PT. Adhi Karya (Persero)
Tbk.
SHE-Q & Fire Building Relocation Bontang – East Kalimantan Electrical & Instrument 521-0/030/VIII/2007 August 16, 2007
29January 07, 2008 – February 01, 2008 PT. Kaltim Methanol Industri Restroke Control Valve & Rekalibrasi
Transmitter
Bontang – East Kalimantan Calibration 015/SPK-KMI/LOG/I/2008 January 04,2008
30February 2008 – July 2008 Total E & P Indonesia PT. Perdana Karya Perkasa Bekapai Control Room Relocation (MRS B-
345)
Handil – East Kalimantan Electrical & Instrument 4500004683January 16, 2008
31April 21, 2008 – May 22, 2008 PT. Promatcon Tepatguna Control Systems Retrofit Duri – Riau Manpower Supply 038/IV-PTG/SPK-CPI/2008 March 17, 2008
32April 10, 2008 – August 25, 2008 PT. DSM Kaltim Melamine DCS Migration Bontang – East Kalimantan Manpower Supply L26559 April 18, 2008
33July 2008 – August 2008 PT. Medco Energy PT. Kutilang Paksi Mas Rental Compressor Gas Tiaka – Central Sulawesi Electrical, Instrument, &
Calibration
053/KPM/SO/V/08 May 02, 2008
34July 2008 – August 2008 PT. DSM Kaltim Melamine Construction of DKM Fire Alarm System Bontang – East Kalimantan Electrical & Instrument L26627 June 22, 2008
35July 1, 2008PT. DSM Kaltim Melamine Fire Alarm System Bontang – East Kalimantan Material Supply L26799 June 30, 2008
36June – July 2008 VICO Indonesia PT. Perdana Karya Nilam & Badak Well Head Compressor
Phase-II
Muara Badak – East
Kalimantan
Electrical, Instrument, &
Calibration
104/PK-PROJ/SMD-VII/2008 July 05, 2008
37September 2008 – December 2008 Total E & P Indonesia Pengadaan Material Handil – East Kalimantan Material Supply 4300011153July 11, 2009
38September 2008 – September 2009 Total E & P Indonesia PT. Perdana Karya Perkasa
Tbk.
Handil Well Connection 2008 – 2009 Handil – East Kalimantan Electrical & Instrument VII/2008 (4600001798) 110/PKP-KPU/SMD- July 26, 2008
39December 1, 2008PT. DSM Kaltim Melamine Modify of Power Supply Emergency Air
Compressor (K-9450)
Bontang – East Kalimantan Electrical L27121(1) November 21, 2008
40December 07, 2008 – September 07,
2009
PT. Medco E & P Lematang PT. Inti Karya Persada Tehnik Singa Gas Development Lematang Block – South Sumatra Electrical SGA-L-IJKPU-001 November 10, 2008
41January 2009 – March 2009 VICO Indonesia PT. Perdana Karya Perkasa
Tbk.
In Plant Facilities Construction (#39290) Nilam – East Kalimantan Electrical & Instrument 124/PKP-KPU/SMD-I/2009 January 08, 2009
42March 2009 – June 2009 VICO Indonesia PT. Perdana Karya Perkasa
Tbk.
Construction of Nilam Satellite#6 VLP Gas
Compression Facilities
Nilam – East Kalimantan Electrical, Instrument, & Calibration 113/PKP-KPU/SMD-X/2008 (39650) October 29, 2008
43June 2009 – August 2009 Total E & P Indonesia PT. Perdana Karya Perkasa
Tbk.
Handil Well Connections 2009 Handil – East Kalimantan Electrical & Instrument 156/PKP-KPU/SMD-VI/2009 (4600002195) June 30, 2009
44October 2009 – January 2010 Total E & P Indonesia PT. Perdana Karya Perkasa
Tbk.
Handil Well Connections 2009 – 2010 Handil – East Kalimantan Electrical & Instrument 177/PKP-KPU/SMD-X/2009 (4600002340) October 27, 2009
45December 2009 – January 2010 VICO Indonesia PT. Perdana Karya Perkasa
Tbk.
In Plant Facilities Construction (#42900) Mutiara – East Kalimantan Electrical & Instrument 193/PKP-KPU/SMD- XII/2009 December 07, 2009
46November 1, 2009PT. Pupuk Kalimantan Timur PT. Schneider Indonesia PKT De-min Bontang – East Kalimantan Manpower Supply 2103 165881 November 13, 2009
47March 1, 2010VICO Indonesia PT. Kaliraya Sari Electric / Instrument Gas Lift Mutiara – East Kalimantan Electrical, Instrument, &
Calibration
KRS/IDS/SPK/LX/03/10/01
9
March 18, 2010
48May 1, 2010PT. Promatcon Tepatguna Kalibrasi Instrument KODECO Gresik – East Jawa Manpower Supply 054/V-PTG/WO-KD/2010 May 21, 2010
49June 2010 – June 2011 Total E & P Indonesia PT. Perdana Karya Perkasa
Tbk.
Handil Well Connection 2010 – 2011 Handil – East Kalimantan Electrical & Instrument 025/PKP-KPU/PROJ/SMD- V/2010 (4600002529) May 14, 2010
50June 01, 2010 – June 10, 2010 PT. DSM Kaltim Melamine Bantuan Man Power K3601B Bontang – East Kalimantan Manpower Supply 4500117800June 07, 2010
51June 1, 2010PT. DSM Kaltim Melamine Construction of COD-509, 510 & 511 Bontang – East Kalimantan Electrical & Instrument 4500117644May 26, 2010
52June 1, 2010PT. DSM Kaltim Melamine Pasang Flowmeter FE/FT-9601 di Discharge Bontang – East Kalimantan Electrical & Instrument 4500117647May 26, 2010
53June 1, 2010PT. DSM Kaltim Melamine Power Distribusion Bontang – East Kalimantan Electrical, Instrument, &
Material Supply
4500117772June 02, 2010
54October 2010 – December 2010 JOB Pertamina – Talisman
Jambi Merang
PT. Suluh Ardhi Engineering EPC Gas Metering Station Musi Banyu Asin – South Sumatera Electrical & Instrument GMS-GL-CT-EI-001 September 08, 2010
55October 04, 2010 – November 04, 2010 PT. Kaltim Methanol IndustriConduit Replacement, Re-calibration
Transmitter, Restroke control Valve & Valve
Diaphragm Replacement
Bontang – East Kalimantan Electrical, Instrument, &
Calibration
035/SPK-KMI/LOG/X/2010 October 02, 2010
56November 2010 – February 2011 VICO Indonesia PT. Perdana Karya Perkasa
Tbk.
Flowline Installation Services Semberah – East Kalimantan Electrical & Instrument 068/PKP-KPU/PROJ/SMD- XI/2010 (42980) November 04, 2010
57December 2010 – January 2011 VICO Indonesia PT. Perdana Karya Perkasa
Tbk.
Flowline Installation Services Semberah – East Kalimantan Electrical & Instrument 070/PKP-KPU/PROJ/SMD- XII/2010 (42980) December 10, 2010
58November 27, 2010 – January 12, 2011 PT. Pupuk Kalimantan Timur PT. JGC Indonesia Pembangunan Sarana Transportasi Bahan
Baku dan Utilitas untuk Pabrik
Bontang – East Kalimantan Instrument & Calibration 7758/SP-BTG/2010 August 16, 2010
59January 2011 – April 2011 PT. Milda PT. Rekayasa Industri Tie-in KPA to KNI Bontang – East Kalimantan Electrical & Instrument 001/MLD-SPK/BTG/I/2011 January 17, 2011
60February 2011 – May 2011 ConocoPhilips Indonesia PT. Kelsri Dayung Early Gas Compressor Musi Banyu Asin – South
Sumatera
Electrical, Instrument, &
Calibration
0294/DIR/1000/II/2011 February 07, 2011
61January 2011 – February 2011 PT. Pupuk Kalimantan Timur
Tbk
PT. JGC Indonesia Install 5 Unit Manual Level Indicator Bontang – East Kalimantan Instrument WO-JH/KPU-005/PMT/2011 January 15, 2011
62February 2011 – March 2011PT. Pupuk Kalimantan Timur
Tbk. Divisi Jasa Pelayanan
Pabrik
Assembling Electrical Sarana Transportasi
KNI
Bontang – East Kalimantan Electrical & Manpower Supply 218/SPK/LOG-JPP/II/2011 February 07, 2011
63April 2011 – May 2011 VICO Indonesia PT. Milway Engineering Retrofit Badak Compressor Muara Badak – East
Kalimantan
Electrical, Instrument, &
Calibration
035/EPC491/C103/II-11 February 23, 2011
64April 12, 2011 – June 14, 2011 PT. Sumatera Prima
Fibreboard
Electrical Energy Plant Package Palembang – South Sumatera Electrical 0294/DIR/1000/IV/2011 April 12, 2011
65May 09, 2011 – May 08, 2012 PT. Badak NGLImprovement of All Conduit Installation at
Cooling Water Module #2 (Electrical
Portion)
Bontang – East Kalimantan Electrical & Material Supply CA-11003 May 02, 2011
66May 14, 2011 – August 27, 2011 PT. Kaltim Industrial Estate Instalasi Kabel Fiber Optik Bontang – East Kalimantan Installation Fiber Optic
Cable & Material Supply
08.03/SP/DIR/KIE/V/2011 May 13, 2011
67June 15, 2011 – August 15, 2011 PT. Kaltim Pasific Amoniak PT. Rekayasa Industri Install DCS & ESD Panel, Termination &
Install Cable Tray
Bontang – East Kalimantan Electrical ANTA-Y2-J0-000-CT-006 June 15, 2011
68June 2011 – July 2011 PT. Sumatera Prima
Fibreboard
Additional Works Electrical Installation for
Metso Cable (Refiner Area) and Group 3200,
Area Glow Kitchen
Indralaya – South Sumatera Electrical PO/11/06/0181 June 14, 2011
69July 1, 2011PT. Sumatera Prima
Fibreboard/PT. Schneider
Indonesia
Superthin MDF Plant Indralaya – South Sumatera Electrical 2103 205994 July 13, 2011
70July 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Grounding Jumper Motor,
Tray at Area Energy Plant, Refiner & Glue
Area
Indralaya – South Sumatera Electrical PO/11/07/0156 July 14, 2011
71July 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Install Cable Tray, Cable
Pulling & Termination Cable Chiller area
Indralaya – South Sumatera Electrical PO/11/07/0158 July 15, 2011
72August 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Cable Pulling &
Termination for HT 40 at SR-02
Indralaya – South Sumatera Electrical PO/11/08/0307
73August 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Install, Pulling &
Termination Glue Transfer Area
Indralaya – South Sumatera Electrical PO/11/08/0308
74July 2011 – December 03, 2011 ConocoPhilips Indonesia PT. Inti Karya Persada
Tehnik
Suban Bypass Plant Suban – South Sumatera Electrical & Instrument NSB-SCA-SA-008 July 04, 2011
75September 05, 2011 – February 02, 2012 VICO Indonesia PT. Kaliraya Sari CBM Side Well & Central Well (NI) Pamaguan – East Kalimantan Electrical & Instrument KRS
KPU/SPK/NI/09/11/003
September 05, 2011
76October 27, 2011 – November 18, 2011 PT. OCI Kaltim Melamine Sirene OCI Kaltim Melamine Bontang – East Kalimantan Installation Alarm &
Material Supply
4500120859October 27, 2011
77October 2011 – November 2011 Total E & P Indonesia PT. Koneksindo Karya
Mandiri
Testing, Termina & Spilicir Senipah – East Kaltimantan Testing & Splicing Fiber Optic Cable 055/KKM-PO/IX/11
78December 2011 – January 2012 PT. Kaltim Parna Industri Supply Man Power Elektrikal & Instrument
Skill
Bontang – East Kalimantan Manpower Supply SPK/XII/2011(14328) 0315/KPI- December 07, 2011
79December 1, 2011VICO Indonesia PT.Perdana Karya Perkasa
Tbk.
Flowline Installation Services (Northern
Mutiara Mini Station-II, AFE-61308, VICO
Indonesia)
Handil – East Kalimantan Electrical, Instrument, &
Calibration
093/PKP-KPU/PROJ/SMD
XII/2011 (#DA51330)
December 01, 2011
80January 2012 – April 2012 VICO Indonesia PT.Perdana Karya Perkasa
Tbk.
Flowline Installation Services (VLP Gas
Compression, Nilam – Satelitte #2, VICO
Indonesia)
Handil – East Kalimantan Electrical, Instrument, &
Calibration
001/PKP-KPU/PROJ/SMD
I/2012 (AFE-061310-8721-3784
#51330)
January 07, 2012
81January 1, 2012PT. Schneider ElectricAdditional kabel Installasi st site for
Superthin Project for – Group 2400, – Group
4500 SP, – 5400, – Grou 5500 and Grounding
Palembang – South Sumatera Electrical 2103 217019
82January 2012 – July 12, 2012 PT. Black Bear Resources
Indonesia
Installation of Street Lighting & Grounding
System, EMP Plant PT. BBRI
Bontang – East Kalimantan Electrical 07/SPK-BBRI/I/2012 January 18, 2012
83February 2012 – March 2012 PT. Black Bear Resources
Indonesia
Pemasangan Main Cable Ladder & Tray
Untuk Instrument, EMP Plant PT. BBRI
Bontang – East Kalimantan Instrument 025/SPK-BBRI/II/2012 February 06, 2012
84April 2012 – May 2012 PT. Black Bear Resources
Indonesia
Additional Grounding Instrument &
Electrical EMP PLANT, PT. BBRI
Bontang – East Kalimantan Electrical 054/SPK-BBRI/IV/2012 April 05, 2012
85April 2012 – June 2012 PT. Black Bear Resources
Indonesia
Electrical Cable Pulling Tie In dari KDM ke
Substation EMP PLANT, PT.BBRI
Bontang – East Kalimantan Electrical 055/SPK-BBRI/IV/2012 April 05, 2012
86March 2012 – April 2012 PT. Black Bear Resources
Indonesia
Pemasangan Main Cable Ladder & Tray
Untuk Elektrikal , EMP Plant PT. BBRI
Bontang – East Kalimantan Instrument 056/SPK-BBRI/II/2012 March 14, 2012
87June 1, 2012PT. Black Bear Resources
Indonesia
Supply Material Lighting Street Junction Box
di EMP Plant PT. BBRI
Bontang – East Kalimantan Material Supply 094/SPK/BBRI-KPU/VI/2012 June 19, 2012
88June 2012 – August 2012 PT. Black Bear Resources
Indonesia
Supply Material & Installasi Junction Box &
Civil Work di EMPT Plant PT. BBRI
Bontang – East Kalimantan Material Supply 093/SPK/BBRI- KPU/VI/2012 June 18, 2012
89June 1, 2012VICO INDONESIA PT. Perdana Karya Perkasa
Tbk.
Inplant & Flowline Surface Facility
(#47750R) – Pamaguan VLP Compressor
Muara Badak – East
Kalimantan
Electrical, Instrument, &
Calibration
057/PKP-KPU/RENT/SMD
VI/2012
June 25, 2012
90June 1, 2012VICO INDONESIA PT. Perdana Karya Perkasa
Tbk.
Calibration,Commissioning, Installation Muara Badak – East Kalimantan Calibration 067/PKP-KPU/PROJ/SMD- VII/2012
91July 01, 2012 – December 30, 2012 PT. Toba Bara Sejahtera, Tbk. PT. Kutilang Paksi Mas IPP Senipah Project – Total In Plant Senipah – East Kalimantan Electrical & Instrument 026/KPMOG/SO/VII/12DN July 01, 2012
92July 25, 2012 – August 25, 2012 ConocoPhilips Indonesia PT. Inti Karya Persada –
Kelsri
EPC LTRO Pipeline Musi Banyu Asin – South Sumatera Scaffolding Rent LTRO-SCA-SA-021 (10031) July 25, 2012
93November 1, 2013PT. Toba Bara Sejahtera, Tbk. PT KPM Kalibrasi Turbine IPP Senipah Area PLTG Senipah – East Kalimantan Electrical & Instrument 057/PO/SNP/KPU
KPM/XI/2013
94August 2012 – December 2013 ConocoPhilips Indonesia PT. Inti Karya Persada Teknik EPC Rawa Modification Musi Banyu Asin – South
Sumatera
Electrical & Instrument RW-LOI-IJSC-010 August 13, 2012
95April 05, 2012 – October 25, 2013 PT. Pupuk Kaltim PT. Inti Karya Persada Teknik Coal Boiler Plant Project Bontang – East Kalimantan Manpower Supply CB-000-C4-CT-075 April 05, 2012
96September 2012 – December 2012 PT. Black Bear Resources
Indonesia
Instrument “Calibration & Installation Work”
EMP Project
Bontang – East Kalimantan Instrument 109/SPK-BBRI/KPU/IX/2012 September 25, 2012
97November 2012 – January 2013 PT. Black Bear Resources
Indonesia
Electrical Plant Installation Work Bontang – East Kalimantan Electrical 118/SPK/BBRI-KPU/XI/2012 November 08, 2012
98November 1, 2012PT. Kaltim Methanol Industri Calibration of transmitter and restroke
Control Valve For Turn Around 2012
Bontang – East Kalimantan Manpower Supply 034/SPK-KMI/LOG/X/2012
99September 1, 2012PT. Toba Bara Sejahtera, Tbk. PT. KPM OIL & GAS Instalasi Elektrical & Instrumentasi PLTG
Senipah 2 X 41 MW
Senipah – East Kalimantan Electrical & Instrument 046/KPMOG/SO/IX/12DN
100January 19, 2013 – February 14, 2013 PT. Kaltim Parna Industri PT. Kutilang Paksi Mas Kalibrasi Instrument X-Mitter, Control Valve Bontang – East Kalimantan Instrument 0502/KPI-SPK/XII/2012
(16346)
December 30, 2012
101January 1, 2013VICO INDONESIA PT. Kutilang Paksi Mas Electrical & Instrument Work for VLP
Compressor M#8
Muara Badak – East
Kalimantan
Electrical & Instrument CK-06-M8 / SPK / QQ /14/01/2013
102February 2013 – November 24, 2014 PT. Pupuk Kalimantan TimurPT. Inti Karya Persada
Tehnik – PT. TOYO
Engineering Corporation
Kaltim-5 Bontang – East Kalimantan Instrument K5-00-C3-CT-034 February 01, 2013
103May 1, 2013PT. Black Bear Resources
Indonesia
Pemasangan peralatan listrik dan
Instrumentasi
Bontang – East Kalimantan Electrical & Instrument B049/SPK-BBRI/V/2013 May 08, 2013
104July 2013 – September 2013 PT. Black Bear Resources
Indonesia
Pemasangan / Penarikan Kabel ke Bukit
Kusnodo
Bontang – East Kalimantan Manpower Supply B116/SPK-BBRI/VII/2013 July 04, 2013
105September 1, 2013VICO INDONESIA PT. Cipta Karsa Konstruksi untuk VLP GAS Compressor
Mutiara 8 (PURCHASE)
Handil – East Kalimantan Electrical & Instrument M8/SPK/QQ/14/01/2013 CK-06-
106September 1, 2013VICO INDONESIA PT. Cipta Karsa Mutiara Gas Development Project Handil – East Kalimantan Electrical & Instrument CK-22-
MCP/SPK/QQ/15/08/2013
107September 2013 – December 08, 2014 PT. Toba Bara Sejahtera, Tbk. PT. Kutilang Paksi Mas IPP PLTG Senipah Senipah – East Kalimantan Electrical & Instrument 012/KPM-KPU/PKS/X/2013 September 30, 2013
108October 2013 – December 2013 PT. Black Bear Resources
Indonesia
PT. Kutilang Paksi Mas Pemasangan Lampu Penerangan Tambahan dan Kalibrasi Peralatan Instrument Bontang – East Kalimantan Instrument B237/SPK-BBRI/X/2013 October 03, 2013
109November 18, 2013 – December 12,
2013
PT. Kaltim Methanol Industri Restroke Control Valve and Calibration of Transmitter For Turn Around 2013 Bontang – East Kalimantan Electrical & Instrument 033/SPK-KMI/LOG/XI/2013 November 06, 2013
110April 21, 2014 – December 20, 2014 PT. Badak NGL Dry Chemical at 24-D-6 (33-T-1452)
Improvement
Bontang – East Kalimantan Improvement Fire Estinguisher CA-14002 April 28, 2014
111June 11, 2014 – March 31, 2015 Mobil Cepu Ltd PT. Tripatra Engineers &
Constructor
Banyu Urip Project Bojonegoro – East Jawa Electrical 9533-INWO-3240000545 Rev. 0 June 11, 2014
112June 11, 2014 – October 31, 2014 JOB Pertamina Talisman
Jambi Merang
PT. Suluh Ardhi Engineering EPC Gas Metering At Grissik Grissik – South Sumatra Electrical & Instrument GRS-CT-N-003 March 17, 2014
113July 2014 – October 2014 VICO PT. Kaliraya Sari VICO Compressor Pamaguan P-8 Pamaguan – East Kalimantan Electrical & Instrument KRS-13-/SPK/OX/23/6/2014 June 23, 2014
114September 02, 2014 – December 05,
2014
PT. Kaliraya Sari Manpower Supply for Water Injection Facility of Ampu Pressure, Maintenance Project East Kalimantan Manpower Supply BFK/SPK/AG/09/14/014 KRS- September 02, 2014
115September 1, 2014VICO PT. Kaliraya Sari Kalibrasi Gas Lift Pamaguan – East Kalimantan Electrical & Instrument
116September 2014 – October 2014 PT. Toba Bara Sejahtera, Tbk. PT. Kutilang Paksi Mas Commissioning 2 Unit GTG at PLTG
Senipah
Senipah – East Kalimantan Electrical & Instrument
117October 01, 2014 – December 29, 2015 PT. Pupuk Sriwidjaja
Palembang
PT. Toyo Engineering
Corporation
Pusri – II B Project Palembang – South Sumatera Electrical & Instrument BA-1066-AX-44-01 December 24, 2013
118October 01, 2014 – October 30, 2015 BP Berau Ltd. PT. Wijaya Karya (Persero)
Tbk
Tie-in Electrical Power & Instrument Untuk
Temporary Facility
West Papua Electrical & Instrument TP.02.01/NCDT.TGH/0292A /X/2014 Add.1 September 29, 2015
119October 20, 2014 – December 03, 2014 PT. Kaltim Methanol Industri Calibration of Transmitter For Turn Around
2014
Bontang – East Kalimantan Calibration KMI/LOG/VIII/2014 025/SPK- August 26, 2014
120November 24, 2014 – December 29,
2014
PT. Kaltim Daya Mandiri Pulling Cable Trafo Tursina Bontang – East Kalimantan Electrical 29/SPK/DIR/KDM/BTG/X/ 2014 October 24, 2014
121December 01, 2014 – September 21,
2017
PT. Pupuk Kalimantan Timur PT. Inti Karya Persada Tehnik (IKPT) Kaltim 5 – Manpower dan Tools Supply Bontang – East Kalimantan Manpower dan Tools Supply K5-00-C3-CT-034B November 27, 2014
122January 01, 2015 – December 31, 2015 Mobil Cepu Ltd PT. Tripatra Engineers &
Constructor
Banyu Urip Project Bojonegoro – East Jawa Manpower Supply 9533-ELWO-3240001070 Rev.2 September 28, 2015
123July 24, 2015 – August 15, 2015 PT. Pupuk Kalimantan Timur Pekerjaan Perbaikan Instalasi Listrik
Conveyor System
Bontang – East Kalimantan Installation of Electrical Conveyor System 298/SPPJ-BTG/2015 July 1, 2015
124August 04, 2015 – October 31, 2017 BP Berau Ltd. PT. Wijaya Karya (Persero)
Tbk
New Condensate & Diesel Tanks Bintuni – West Papua Electrical & Instrument TP.01.03/U.DEP.IP.NCDT- TGH/0855/III/2015 March 25, 2015
125November 02, 2015 -June 30, 2016 PT. Tropik Energi Pandan PT. Sinergi Era Cemerlang Tropik Energi Pandan Lubuk Linggau – South Sumatra Electrical & Instrument 098/SEC-PO/X/2015 October 07, 2015
126January 11, 2016 – May 06, 2017 PT. Pupuk Sriwidjaja
Palembang
PT. Toyo Engineering
Corporation
Pusri – II B Project Palembang – South Sumatera Manpower Supply BA-1066-AX-82-01 January 08, 2016
127February 08, 2016 – February 09, 2017 ConocoPhilips Indonesia PT. Inti Karya Persada
Tehnik (IKPT)
Dayung Compression Phase-2 (DC-2
Project)
Dayung – South Sumatra Electrical & Instrument DC2-CNT-CON-004-E February 15, 2016
128February 08, 2016 – March 06, 2016 PT. Kaltim Parna Industri Calibration Transmitter, Control Valve, &
Switch All Area
Bontang – East Kalimantan Calibrasi Transmitter, Control Valve, & Switch 055/KPI/CA/I/2016 (19514) February 08, 2016
129March 21, 2016 – April 30, 2017 PT. Pertamina PT. Wijaya Karya (Persero)
Tbk
Pengembangan Terminal BBM Pulau Sambu Batam Electrical & Instrument TP.01.03/U.DEP.IP.P.SAMBU /0461/III/2016 March 21, 2016
130July 21, 2016 – April 18, 2017 ConocoPhilips Indonesia PT. Shaftindo Energi Suban #15 Project Suban – South Sumatera Electrical & Instrument LOG/16/1622 July 19, 2016
131December 05, 2016 – January 31, 2017 ConocoPhilips Indonesia PT. Shaftindo Energi Suban Laydown Suban – South Sumatera Electrical & Instrument SO/16/0056 November 29, 2016
132November 15, 2016 – October 05, 2018 PT. Synthetic Rubber
Indonesia
PT. Inti Karya Persada
Tehnik
120 KTA Synthetic Rubber – U3 Project Cilegon – Banten Instrument AY4501 November 29, 2016
133February 13, 2017 – December 04, 2017 Millenium Challenge Account –
Indonesia (MCA-Indonesia)
PT. Inti Karya Persada
Tehnik
Solar Photovoltaic Electricity for
Karampuang Island Project
Mamuju – West Sulawesi Electrical, Instrument, & Civil Building Works AW-4401 February 10, 2017
134July 11, 2017 – April 28, 2018 Millenium Challenge Account –
Indonesia (MCA-Indonesia)
PT. Inti Karya Persada
Tehnik
Solar Photovoltaic Electricity for Tomia
Project
Wakatobi – Southeast Sulawesi Electrical, Instrument, & Civil Works WKB-IKPT-SC-LOI-001 July 05, 2017
135August 2017 – September 2017 PT. Pupuk Kalimantan Timur PT. Siemens Indonesia Upgrade Control System Quadrant Arm
Loader
Bontang – East Kalimantan Electrical 4507471980May 02, 2017
136August 2017 – August 29, 2017 PT. Kaltim Parna Industri Kalibrasi Transmitter, Switch & Control
Valve
Bontang – East Kalimantan Calibration 137/26152/KPI- SPK/VII/2017 July 24, 2017
135September 07, 2017 – October 07, 2017 PT. Badak NGL PT. ABB Sakti Industri Site Installation Work Bontang – East Kalimantan Site Support 3762006509July 20, 2017
136October 08, 2017 – October 21, 2017 PT. Badak NGL PT. ABB Sakti Industri Additional Mandays Bontang – East Kalimantan Site Support 3762006915December 19, 2017
137December 15, 2017 – August 13, 2018 PT. Oki Pulp & Paper Mills PT. Timas Suplindo Oki – Tissue Machine Project Ogan Komering Ilir – South
Sumatera
Electrical, Instrument, &
Automation
217/TMS-HO/PKS
LI/XII/2017
December 15, 2017
136March 27, 2018 – May 15, 2018 PT. Oki Pulp & Paper Mills PT. Timas Suplindo Oki – Tissue Machine Project Ogan Komering Ilir – South
Sumatera
Electrical, Instrument, &
Automation
036/TMS-HO/PKS
LI/III/2017
March 04, 2018
137April 25, 2018 – May 25, 2018 PT. Oki Pulp & Paper Mills PT. Timas Suplindo Oki – Tissue Machine Project Ogan Komering Ilir – South
Sumatera
Jasa Penarikan Kabel Power TSON/PO/1804-02768 April 25, 2018
138October 1, 2018PT. Oki Pulp & Paper Mills PT. Timas Suplindo Oki – Tissue Machine Project Ogan Komering Ilir – South
Sumatera
Manpower Acceleration
Tahap 1
TSON/PO/1810-05670 October 02, 2018
139December 15, 2017 – September 07,
2018
PT. Industri Nabati Lestari PT. Wijaya Karya (Persero) Tbk Proyek Pembangunan Pabrik Minyak Goreng 600.000 TPY Sei Mangkei, Simalungun – North Sumatera Electrical & Instrument TP.01.01/U.DEP.IP.D.PMG/2 543/XII/2017 December 15, 2017
140March 01, 2018 – March 22, 2018 PT. Chandra Asri
Petrochemical Tbk
PT. Inti Karya Persada
Tehnik
NPE Project 400 KTA New Swing Plant of
HDPE, LLDPE and mLLDPE
Cilegon – Banten Tie-In Instrument NPE-WO-AX-4502 January 31, 2018
141March 20, 2018 – March 22, 2018 PT. Chandra Asri
Petrochemical Tbk
PT. Inti Karya Persada
Tehnik
NPE Project 400 KTA New Swing Plant of
HDPE, LLDPE and mLLDPE
Cilegon – Banten Support VSM Yokogawa for Tie-In Instrument NPE-CPL-CNT-AX-4504 March 20, 2018
142April 19, 2018 – June 30, 2018 PT. Chandra Asri
Petrochemical Tbk
PT. Artha Teknik Abadi NPE Project Cilegon – Banten Cathodic Protection Work 286/PO/ATA/IV/18/Rev.02 April 17, 2018
143May 16, 2018 – October 15, 2018 PT. Synthetic Rubber
Indonesia
PT. Inti Karya Persada
Tehnik
120 KTA Synthetic Rubber – U3 Project Cilegon – Banten Supply Manpower AY4821 May 15, 2018
144May 31, 2018 – July 31, 2018 PT. Riau Andalan Pulp &
Paper
PT. Timas Suplindo CS2 Recovery & Spinbath Kerinci – Riau Electrical 083/TMS-HO/PKS- LI/VI/2018 May 31, 2018
145June 25, 2018 – July 31, 2019 PT. Chandra Asri
Petrochemical Tbk
PT. Inti Karya Persada
Tehnik
400 KTA New Swing Plant HDPE, LLDPE,
and mLLDPE
Cilegon – Banten Electrical NPE-CPL-LOI-AX-4401 May 10, 2018
146July 2018 – March 2019 PT. PLN (Persero) PT. Satyamitra Surya Perkasa PLTU Lontar Project Lontar – Tangerang Installation Cable Tray,
Lighting & Instrument
100033283July 11, 2018
147July 23, 2018 – December 31, 2018 BP Berau Ltd.CSTS JO (PT. Tripatra
Engineers & Constructors,
PT. Chiyoda International
Indonesia, PT. Saipem
Indonesia, PT. Suluh Ardhi
Engineering)
LAN, PA/GA, CCTV Installation for
Tangguh Onshore Expansion EPC Project
Bintuni – West Papua Installation, Testing & Commissioning 1235823August 10, 2018
148October 16, 2018 – December 20, 2018 PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk
EPCC Pengembangan & Modernisasi PG
Assembagoes Situbondo
Situbondo – East Java Electrical ASSEMBAGOES/086/X/2018 TP.02.01/U.DEP.IP.PG August 16, 2018
149October 18, 2018 – December 20, 2018 PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk
EPCC Pengembangan & Modernisasi PG
Assembagoes Situbondo
Situbondo – East Java Electrical ASSEMBAGOES/089/X/2018 TP.02.01/U.DEP.IP.PG August 18, 2018
150October 20, 2018 – December 20, 2018 PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk
EPCC Pengembangan & Modernisasi PG
Assembagoes Situbondo
Situbondo – East Java Electrical ASSEMBAGOES/091/X/2018 TP.02.01/U.DEP.IP.PG August 18, 2018
151October 15, 2018 – February 26, 2019 PT. Pindo Deli 3 PT. Timas Suplindo Pindo Deli Karawang Project Karawang – West Java Electrical & Instrumentation TSON/PO/1810-05742 October 05, 2018
152November 1, 2018PT. PLN (Persero) PT. Satyamitra Surya Perkasa PLTU Lontar Project Lontar – Tangerang Kalibrasi Alat Pressure
Gauge with Switch
100039098November 22, 2018
153November 19, 2018 – February 14, 2019 PT. Pupuk Kalimantan Timur PT. Inti Karya Persada
Tehnik
Kaltim-5 Project (Shutdown Activity 2018) Bontang – East Kalimantan Electrical & Instrumentation AX-4401 November 19, 2018
153January 23, 2019 – June 30, 2019 PT. Pupuk Sriwidjaja
Palembang
PT. Wijaya Karya (Persero)
Tbk
Proyek Pembangunan Pabrik NPK Fusion II
Kapasitas 2×100.000 MTPY PT. Pupuk
Sriwidjaja
Palembang – South Sumatera Electrical & Instrumentation TP.01.03/U.DEP.IP.NPKII/18
9/I/2019
January 23, 2019
153February 01, 2019 – January 31, 2020 BP Berau Ltd.CSTS JO (PT. Tripatra
Engineers & Constructors,
PT. Chiyoda International
Indonesia, PT. Saipem
Indonesia, PT. Suluh Ardhi
Engineering)
Supply of Construction Manpower Onshore
LNG EPC for Tangguh Expansion Project
Bintuni – West Papua Supply Manpower 5000036918January 30, 2019
154March 01, 2019 – September 01, 2019 PT. PLN (Persero) PT. Satyamitra Surya Perkasa PLTU Lontar Project Lontar – Tangerang Pulling Cable &
Termination
100042989March 01, 2019
155March 11, 2019 – May 11, 2019 PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk dan
Jasa Instalasi Elektrikal & Instrument untuk
Area Boiler Package
Kudus – Central Jawa Electrical & Instrumentation 066/SPK/III/BMSC/2019 March 06, 2019