NOSCHEDULE (START DATE – END
DATE)
CLIENTMAIN CONTRACTORPROJECT NAMELOCATIONSCOPE OF WORKCONTRACT NO.CONTRACT DATE 
1May 22, 2004 – December 20, 2004VICO IndonesiaPT. Perdana KaryaVLP CompressionNilam, Samarinda – East
Kalimantan
Electrical & Instrument048.Plan/PK-PKU/Smd-V/04May 22, 2004
2July 14, 2004 – October 24, 2004VICO IndonesiaPT KELSRIConstruction of Samberah S-13 VLP Gas
Compression
Samberah – East KalimantanConstruction, Electrical, Instrument, & Calibration2004 WO 199July 09, 2004
3December 23, 2004 – January 23, 2005VICO IndonesiaPT. Perdana KaryaReplacement of Orrifice Plate for Badak Well
Surveillance Phase II
Muara Badak – East
Kalimantan
Calibration193/SPK-BDK/XII/2004December 20, 2004
4December 23, 2004 – January 23, 2005VICO IndonesiaPT. Perdana KaryaDrill Hole Pipe Support & Calibration for
Badak Well Surveillance Phase II
Muara Badak – East
Kalimantan
Calibration192/SPK-BDK/XII/2004December 20, 2004
5March 15, 2005 – April 18, 2005PT. Banpu IndomincoPT. SAS InternasionalMarine Monitoring SystemBontang – East KalimantanConstruction00371-SUBCONT-INS-009March 08, 2005
6March 07, 2005 – April 20, 2005UnocalPT. Perdana KaryaCEMSLawe-Lawe Terminal,
Balikpapan – East Kalimantan
Material Supply, Electrical,
& Instrument
072.Plan/PK-KPU/Smd-III/05March 17, 2005
7July 09, 2005 – December 20, 2005VICO IndonesiaPT. Perdana KaryaVLP CompressionMuara Badak – East
.Kalimantan
Electrical & Instrument075/PK-KPU/Smd-VII/05July 19, 2005
8August 01, 2005 – August 04, 2005VICO IndonesiaPT. Perdana KaryaTelemetryMuara Badak – East
Kalimantan
Calibration715/SPK/BDK/VIII/2005August 01, 2005
9August 11, 2005 – September 11, 2005EMP Kangean LimitedPT. Perdana KaryaCompressor Dismantling C-8100 & C-8500Pulau Pagerungan – East JawaElectrical & Instrument0102/PK-KPU/Smd-VIII/05August 18, 2005
10September – October 2005EMP Kangean LimitedPT. Perdana KaryaPagerungan Well ConnectionPagerungan Base – East JawaElectrical & Instrument0104/PK-KPU/Smd-VIII/05August 18, 2005
11October 1, 2005EMP Kangean LimitedPT. Perdana KaryaCompressor Dismantling C-1501, 1502, 1503Pagerungan Plant, Pagerungan
Base – East Jawa
Electrical & Instrument0107/PK-KPU/Smd-X/05October 24, 2005
12September 01, 2005 – June 30, 2006PT. Badak NGLPT. SAS InternasionalHMCS 1000 ImprovementBontang – East KalimantanInstallation Instrument &
Control System
CA-04047August 26, 2005
13November 07, 2005 – December 31,
2005
PT. Badak NGLPT. SAS InternasionalReplacement of Marine Monitoring System at Dock #2Bontang – East KalimantanEngineering & ConstructionC-05039August 26, 2005
14January 12, 2006 – March 31, 2006VICO IndonesiaPT. Yasa Industri NusantaraConstruction of Badak Compressor RestageMuara Badak – East
Kalimantan
Electrical & Instrument002/05.34608/YIN- KPU/SPB/2006January 12, 2006
15January 26, 2006 – February 02, 2006PT. Kaltim Methanol IndustriRestroke Control Valve & Rekalibrasi
Transmitter
Bontang – East KalimantanCalibrationE033/PO-KMS/I/2006January 13, 2006
16March 01, 2006 – March 31, 2006PT. Syrindo Mono IndonesiaPT. Rekayasa EngineeringFuel Oil Blending FacilityCilegon – BantenInstallation Steam Tracing
Material
MFO-01-PR-CT-002March 01, 2006
17April 1, 2006EMP Kangean LimitedPT. Perdana KaryaPulling Power Cable Construction PipelineP. Sepanjang, Pagerungan Base –
East Jawa
Pulling Cable 3 Line x 1.5
km
001/PK-KPU/Smd-IV/06April 04, 2006
18May 2006 – June 2007PT. Badak NGLPT. Inti Karya Persada
Tehnik
DCS Centum V ReplacementBontang – East KalimantanElectrical & InstrumentPGV-CD-CR-J-0001March 24, 2006
19June 1, 2006PT. Indominco MandiriPengadaan Barang : Light Meters TM-203Bontang – East KalimantanMaterial SupplyA20610600June 08, 2006
20August 1, 2006PT. Indominco MandiriPemindahan Kabel PowerBontang – East KalimantanConstruction, Electrical &
Material Supply
75/P/IMB-KPU/VIII/2006August 04, 2006
21September 15, 2006 – December 14,
2006
VICO Indonesia/PT.
Promatcom Tepatguna
TCP Retrofit di Nilam (Vico Plant)Muara Badak – East KalimantanElectrical & InstrumentSPK-001/EPC264.KPU/IX- 2006November 07, 2006
22September 1, 2006PT. Badak NGL/PT. GE
Operations Indonesia
Panel Wiring di SIH pada Proyek Shutdown
Train-E PT. Badak NGL
Bontang – East KalimantanManpower Supply
23April 2007 – October 2007Total E & P IndonesiaPT. Perdana Karya220VAC Power Supply for Telecom Cabinet
and Lightning Protection System
Handil – East KalimantanElectrical001/PK-KPU/Total/IV-2007April 10, 2007
24April 20, 2007 – April 19, 2008Total E & P Indonesia/PT.
Promatcon Tepatguna
Installation of 6 Desander Units on Handil
Wells Handil Field
Handil – East KalimantanInstrument4500004382May 03, 2007
25May 01, 2007 – December 31, 2007PT. Badak NGLHalon 1301 Replacement for Loading Dock 1
& 2 and Train “E-H” MCR
Bontang – East KalimantanEngineering, Procurement, & ConstructionC-06197May 01, 2007
26June 07, 2007 – June 12, 2007PT. Megaron SemestaInstrument Commisioning for GDU UnitSamarinda – East KalimantanCommissioning8001April 19, 2007
27June – July 2007PT. Promatcon TepatgunaTotal DesanderHandil – East KalimantanMaterial Supply4500004362June 26, 2007
28August 16, 2007 – August 15, 2008PT. Badak NGLPT. Adhi Karya (Persero)
Tbk.
SHE-Q & Fire Building RelocationBontang – East KalimantanElectrical & Instrument521-0/030/VIII/2007August 16, 2007
29January 07, 2008 – February 01, 2008PT. Kaltim Methanol IndustriRestroke Control Valve & Rekalibrasi
Transmitter
Bontang – East KalimantanCalibration015/SPK-KMI/LOG/I/2008January 04,2008
30February 2008 – July 2008Total E & P IndonesiaPT. Perdana Karya PerkasaBekapai Control Room Relocation (MRS B-
345)
Handil – East KalimantanElectrical & Instrument4500004683January 16, 2008
31April 21, 2008 – May 22, 2008PT. Promatcon TepatgunaControl Systems RetrofitDuri – RiauManpower Supply038/IV-PTG/SPK-CPI/2008March 17, 2008
32April 10, 2008 – August 25, 2008PT. DSM Kaltim MelamineDCS MigrationBontang – East KalimantanManpower SupplyL26559April 18, 2008
33July 2008 – August 2008PT. Medco EnergyPT. Kutilang Paksi MasRental Compressor GasTiaka – Central SulawesiElectrical, Instrument, &
Calibration
053/KPM/SO/V/08May 02, 2008
34July 2008 – August 2008PT. DSM Kaltim MelamineConstruction of DKM Fire Alarm SystemBontang – East KalimantanElectrical & InstrumentL26627June 22, 2008
35July 1, 2008PT. DSM Kaltim MelamineFire Alarm SystemBontang – East KalimantanMaterial SupplyL26799June 30, 2008
36June – July 2008VICO IndonesiaPT. Perdana KaryaNilam & Badak Well Head Compressor
Phase-II
Muara Badak – East
Kalimantan
Electrical, Instrument, &
Calibration
104/PK-PROJ/SMD-VII/2008July 05, 2008
37September 2008 – December 2008Total E & P IndonesiaPengadaan MaterialHandil – East KalimantanMaterial Supply4300011153July 11, 2009
38September 2008 – September 2009Total E & P IndonesiaPT. Perdana Karya Perkasa
Tbk.
Handil Well Connection 2008 – 2009Handil – East KalimantanElectrical & InstrumentVII/2008 (4600001798) 110/PKP-KPU/SMD-July 26, 2008
39December 1, 2008PT. DSM Kaltim MelamineModify of Power Supply Emergency Air
Compressor (K-9450)
Bontang – East KalimantanElectricalL27121(1)November 21, 2008
40December 07, 2008 – September 07,
2009
PT. Medco E & P LematangPT. Inti Karya Persada TehnikSinga Gas DevelopmentLematang Block – South SumatraElectricalSGA-L-IJKPU-001November 10, 2008
41January 2009 – March 2009VICO IndonesiaPT. Perdana Karya Perkasa
Tbk.
In Plant Facilities Construction (#39290)Nilam – East KalimantanElectrical & Instrument124/PKP-KPU/SMD-I/2009January 08, 2009
42March 2009 – June 2009VICO IndonesiaPT. Perdana Karya Perkasa
Tbk.
Construction of Nilam Satellite#6 VLP Gas
Compression Facilities
Nilam – East KalimantanElectrical, Instrument, & Calibration113/PKP-KPU/SMD-X/2008 (39650)October 29, 2008
43June 2009 – August 2009Total E & P IndonesiaPT. Perdana Karya Perkasa
Tbk.
Handil Well Connections 2009Handil – East KalimantanElectrical & Instrument156/PKP-KPU/SMD-VI/2009 (4600002195)June 30, 2009
44October 2009 – January 2010Total E & P IndonesiaPT. Perdana Karya Perkasa
Tbk.
Handil Well Connections 2009 – 2010Handil – East KalimantanElectrical & Instrument177/PKP-KPU/SMD-X/2009 (4600002340)October 27, 2009
45December 2009 – January 2010VICO IndonesiaPT. Perdana Karya Perkasa
Tbk.
In Plant Facilities Construction (#42900)Mutiara – East KalimantanElectrical & Instrument193/PKP-KPU/SMD- XII/2009December 07, 2009
46November 1, 2009PT. Pupuk Kalimantan TimurPT. Schneider IndonesiaPKT De-minBontang – East KalimantanManpower Supply2103 165881November 13, 2009
47March 1, 2010VICO IndonesiaPT. Kaliraya SariElectric / Instrument Gas LiftMutiara – East KalimantanElectrical, Instrument, &
Calibration
KRS/IDS/SPK/LX/03/10/01
9
March 18, 2010
48May 1, 2010PT. Promatcon TepatgunaKalibrasi Instrument KODECOGresik – East JawaManpower Supply054/V-PTG/WO-KD/2010May 21, 2010
49June 2010 – June 2011Total E & P IndonesiaPT. Perdana Karya Perkasa
Tbk.
Handil Well Connection 2010 – 2011Handil – East KalimantanElectrical & Instrument025/PKP-KPU/PROJ/SMD- V/2010 (4600002529)May 14, 2010
50June 01, 2010 – June 10, 2010PT. DSM Kaltim MelamineBantuan Man Power K3601BBontang – East KalimantanManpower Supply4500117800June 07, 2010
51June 1, 2010PT. DSM Kaltim MelamineConstruction of COD-509, 510 & 511Bontang – East KalimantanElectrical & Instrument4500117644May 26, 2010
52June 1, 2010PT. DSM Kaltim MelaminePasang Flowmeter FE/FT-9601 di DischargeBontang – East KalimantanElectrical & Instrument4500117647May 26, 2010
53June 1, 2010PT. DSM Kaltim MelaminePower DistribusionBontang – East KalimantanElectrical, Instrument, &
Material Supply
4500117772June 02, 2010
54October 2010 – December 2010JOB Pertamina – Talisman
Jambi Merang
PT. Suluh Ardhi EngineeringEPC Gas Metering StationMusi Banyu Asin – South SumateraElectrical & InstrumentGMS-GL-CT-EI-001September 08, 2010
55October 04, 2010 – November 04, 2010PT. Kaltim Methanol IndustriConduit Replacement, Re-calibration
Transmitter, Restroke control Valve & Valve
Diaphragm Replacement
Bontang – East KalimantanElectrical, Instrument, &
Calibration
035/SPK-KMI/LOG/X/2010October 02, 2010
56November 2010 – February 2011VICO IndonesiaPT. Perdana Karya Perkasa
Tbk.
Flowline Installation ServicesSemberah – East KalimantanElectrical & Instrument068/PKP-KPU/PROJ/SMD- XI/2010 (42980)November 04, 2010
57December 2010 – January 2011VICO IndonesiaPT. Perdana Karya Perkasa
Tbk.
Flowline Installation ServicesSemberah – East KalimantanElectrical & Instrument070/PKP-KPU/PROJ/SMD- XII/2010 (42980)December 10, 2010
58November 27, 2010 – January 12, 2011PT. Pupuk Kalimantan TimurPT. JGC IndonesiaPembangunan Sarana Transportasi Bahan
Baku dan Utilitas untuk Pabrik
Bontang – East KalimantanInstrument & Calibration7758/SP-BTG/2010August 16, 2010
59January 2011 – April 2011PT. MildaPT. Rekayasa IndustriTie-in KPA to KNIBontang – East KalimantanElectrical & Instrument001/MLD-SPK/BTG/I/2011January 17, 2011
60February 2011 – May 2011ConocoPhilips IndonesiaPT. KelsriDayung Early Gas CompressorMusi Banyu Asin – South
Sumatera
Electrical, Instrument, &
Calibration
0294/DIR/1000/II/2011February 07, 2011
61January 2011 – February 2011PT. Pupuk Kalimantan Timur
Tbk
PT. JGC IndonesiaInstall 5 Unit Manual Level IndicatorBontang – East KalimantanInstrumentWO-JH/KPU-005/PMT/2011January 15, 2011
62February 2011 – March 2011PT. Pupuk Kalimantan Timur
Tbk. Divisi Jasa Pelayanan
Pabrik
Assembling Electrical Sarana Transportasi
KNI
Bontang – East KalimantanElectrical & Manpower Supply218/SPK/LOG-JPP/II/2011February 07, 2011
63April 2011 – May 2011VICO IndonesiaPT. Milway EngineeringRetrofit Badak CompressorMuara Badak – East
Kalimantan
Electrical, Instrument, &
Calibration
035/EPC491/C103/II-11February 23, 2011
64April 12, 2011 – June 14, 2011PT. Sumatera Prima
Fibreboard
Electrical Energy Plant PackagePalembang – South SumateraElectrical0294/DIR/1000/IV/2011April 12, 2011
65May 09, 2011 – May 08, 2012PT. Badak NGLImprovement of All Conduit Installation at
Cooling Water Module #2 (Electrical
Portion)
Bontang – East KalimantanElectrical & Material SupplyCA-11003May 02, 2011
66May 14, 2011 – August 27, 2011PT. Kaltim Industrial EstateInstalasi Kabel Fiber OptikBontang – East KalimantanInstallation Fiber Optic
Cable & Material Supply
08.03/SP/DIR/KIE/V/2011May 13, 2011
67June 15, 2011 – August 15, 2011PT. Kaltim Pasific AmoniakPT. Rekayasa IndustriInstall DCS & ESD Panel, Termination &
Install Cable Tray
Bontang – East KalimantanElectricalANTA-Y2-J0-000-CT-006June 15, 2011
68June 2011 – July 2011PT. Sumatera Prima
Fibreboard
Additional Works Electrical Installation for
Metso Cable (Refiner Area) and Group 3200,
Area Glow Kitchen
Indralaya – South SumateraElectricalPO/11/06/0181June 14, 2011
69July 1, 2011PT. Sumatera Prima
Fibreboard/PT. Schneider
Indonesia
Superthin MDF PlantIndralaya – South SumateraElectrical2103 205994July 13, 2011
70July 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Grounding Jumper Motor,
Tray at Area Energy Plant, Refiner & Glue
Area
Indralaya – South SumateraElectricalPO/11/07/0156July 14, 2011
71July 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Install Cable Tray, Cable
Pulling & Termination Cable Chiller area
Indralaya – South SumateraElectricalPO/11/07/0158July 15, 2011
72August 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Cable Pulling &
Termination for HT 40 at SR-02
Indralaya – South SumateraElectricalPO/11/08/0307
73August 1, 2011PT. Sumatera Prima
Fibreboard
Additional Works Install, Pulling &
Termination Glue Transfer Area
Indralaya – South SumateraElectricalPO/11/08/0308
74July 2011 – December 03, 2011ConocoPhilips IndonesiaPT. Inti Karya Persada
Tehnik
Suban Bypass PlantSuban – South SumateraElectrical & InstrumentNSB-SCA-SA-008July 04, 2011
75September 05, 2011 – February 02, 2012VICO IndonesiaPT. Kaliraya SariCBM Side Well & Central Well (NI)Pamaguan – East KalimantanElectrical & InstrumentKRS
KPU/SPK/NI/09/11/003
September 05, 2011
76October 27, 2011 – November 18, 2011PT. OCI Kaltim MelamineSirene OCI Kaltim MelamineBontang – East KalimantanInstallation Alarm &
Material Supply
4500120859October 27, 2011
77October 2011 – November 2011Total E & P IndonesiaPT. Koneksindo Karya
Mandiri
Testing, Termina & SpilicirSenipah – East KaltimantanTesting & Splicing Fiber Optic Cable055/KKM-PO/IX/11
78December 2011 – January 2012PT. Kaltim Parna IndustriSupply Man Power Elektrikal & Instrument
Skill
Bontang – East KalimantanManpower SupplySPK/XII/2011(14328) 0315/KPI-December 07, 2011
79December 1, 2011VICO IndonesiaPT.Perdana Karya Perkasa
Tbk.
Flowline Installation Services (Northern
Mutiara Mini Station-II, AFE-61308, VICO
Indonesia)
Handil – East KalimantanElectrical, Instrument, &
Calibration
093/PKP-KPU/PROJ/SMD
XII/2011 (#DA51330)
December 01, 2011
80January 2012 – April 2012VICO IndonesiaPT.Perdana Karya Perkasa
Tbk.
Flowline Installation Services (VLP Gas
Compression, Nilam – Satelitte #2, VICO
Indonesia)
Handil – East KalimantanElectrical, Instrument, &
Calibration
001/PKP-KPU/PROJ/SMD
I/2012 (AFE-061310-8721-3784
#51330)
January 07, 2012
81January 1, 2012PT. Schneider ElectricAdditional kabel Installasi st site for
Superthin Project for – Group 2400, – Group
4500 SP, – 5400, – Grou 5500 and Grounding
Palembang – South SumateraElectrical2103 217019
82January 2012 – July 12, 2012PT. Black Bear Resources
Indonesia
Installation of Street Lighting & Grounding
System, EMP Plant PT. BBRI
Bontang – East KalimantanElectrical07/SPK-BBRI/I/2012January 18, 2012
83February 2012 – March 2012PT. Black Bear Resources
Indonesia
Pemasangan Main Cable Ladder & Tray
Untuk Instrument, EMP Plant PT. BBRI
Bontang – East KalimantanInstrument025/SPK-BBRI/II/2012February 06, 2012
84April 2012 – May 2012PT. Black Bear Resources
Indonesia
Additional Grounding Instrument &
Electrical EMP PLANT, PT. BBRI
Bontang – East KalimantanElectrical054/SPK-BBRI/IV/2012April 05, 2012
85April 2012 – June 2012PT. Black Bear Resources
Indonesia
Electrical Cable Pulling Tie In dari KDM ke
Substation EMP PLANT, PT.BBRI
Bontang – East KalimantanElectrical055/SPK-BBRI/IV/2012April 05, 2012
86March 2012 – April 2012PT. Black Bear Resources
Indonesia
Pemasangan Main Cable Ladder & Tray
Untuk Elektrikal , EMP Plant PT. BBRI
Bontang – East KalimantanInstrument056/SPK-BBRI/II/2012March 14, 2012
87June 1, 2012PT. Black Bear Resources
Indonesia
Supply Material Lighting Street Junction Box
di EMP Plant PT. BBRI
Bontang – East KalimantanMaterial Supply094/SPK/BBRI-KPU/VI/2012June 19, 2012
88June 2012 – August 2012PT. Black Bear Resources
Indonesia
Supply Material & Installasi Junction Box &
Civil Work di EMPT Plant PT. BBRI
Bontang – East KalimantanMaterial Supply093/SPK/BBRI- KPU/VI/2012June 18, 2012
89June 1, 2012VICO INDONESIAPT. Perdana Karya Perkasa
Tbk.
Inplant & Flowline Surface Facility
(#47750R) – Pamaguan VLP Compressor
Muara Badak – East
Kalimantan
Electrical, Instrument, &
Calibration
057/PKP-KPU/RENT/SMD
VI/2012
June 25, 2012
90June 1, 2012VICO INDONESIAPT. Perdana Karya Perkasa
Tbk.
Calibration,Commissioning, InstallationMuara Badak – East KalimantanCalibration067/PKP-KPU/PROJ/SMD- VII/2012
91July 01, 2012 – December 30, 2012PT. Toba Bara Sejahtera, Tbk.PT. Kutilang Paksi MasIPP Senipah Project – Total In PlantSenipah – East KalimantanElectrical & Instrument026/KPMOG/SO/VII/12DNJuly 01, 2012
92July 25, 2012 – August 25, 2012ConocoPhilips IndonesiaPT. Inti Karya Persada –
Kelsri
EPC LTRO PipelineMusi Banyu Asin – South SumateraScaffolding RentLTRO-SCA-SA-021 (10031)July 25, 2012
93November 1, 2013PT. Toba Bara Sejahtera, Tbk.PT KPMKalibrasi Turbine IPP Senipah Area PLTGSenipah – East KalimantanElectrical & Instrument057/PO/SNP/KPU
KPM/XI/2013
94August 2012 – December 2013ConocoPhilips IndonesiaPT. Inti Karya Persada TeknikEPC Rawa ModificationMusi Banyu Asin – South
Sumatera
Electrical & InstrumentRW-LOI-IJSC-010August 13, 2012
95April 05, 2012 – October 25, 2013PT. Pupuk KaltimPT. Inti Karya Persada TeknikCoal Boiler Plant ProjectBontang – East KalimantanManpower SupplyCB-000-C4-CT-075April 05, 2012
96September 2012 – December 2012PT. Black Bear Resources
Indonesia
Instrument “Calibration & Installation Work”
EMP Project
Bontang – East KalimantanInstrument109/SPK-BBRI/KPU/IX/2012September 25, 2012
97November 2012 – January 2013PT. Black Bear Resources
Indonesia
Electrical Plant Installation WorkBontang – East KalimantanElectrical118/SPK/BBRI-KPU/XI/2012November 08, 2012
98November 1, 2012PT. Kaltim Methanol IndustriCalibration of transmitter and restroke
Control Valve For Turn Around 2012
Bontang – East KalimantanManpower Supply034/SPK-KMI/LOG/X/2012
99September 1, 2012PT. Toba Bara Sejahtera, Tbk.PT. KPM OIL & GASInstalasi Elektrical & Instrumentasi PLTG
Senipah 2 X 41 MW
Senipah – East KalimantanElectrical & Instrument046/KPMOG/SO/IX/12DN
100January 19, 2013 – February 14, 2013PT. Kaltim Parna IndustriPT. Kutilang Paksi MasKalibrasi Instrument X-Mitter, Control ValveBontang – East KalimantanInstrument0502/KPI-SPK/XII/2012
(16346)
December 30, 2012
101January 1, 2013VICO INDONESIAPT. Kutilang Paksi MasElectrical & Instrument Work for VLP
Compressor M#8
Muara Badak – East
Kalimantan
Electrical & InstrumentCK-06-M8 / SPK / QQ /14/01/2013
102February 2013 – November 24, 2014PT. Pupuk Kalimantan TimurPT. Inti Karya Persada
Tehnik – PT. TOYO
Engineering Corporation
Kaltim-5Bontang – East KalimantanInstrumentK5-00-C3-CT-034February 01, 2013
103May 1, 2013PT. Black Bear Resources
Indonesia
Pemasangan peralatan listrik dan
Instrumentasi
Bontang – East KalimantanElectrical & InstrumentB049/SPK-BBRI/V/2013May 08, 2013
104July 2013 – September 2013PT. Black Bear Resources
Indonesia
Pemasangan / Penarikan Kabel ke Bukit
Kusnodo
Bontang – East KalimantanManpower SupplyB116/SPK-BBRI/VII/2013July 04, 2013
105September 1, 2013VICO INDONESIAPT. Cipta KarsaKonstruksi untuk VLP GAS Compressor
Mutiara 8 (PURCHASE)
Handil – East KalimantanElectrical & InstrumentM8/SPK/QQ/14/01/2013 CK-06-
106September 1, 2013VICO INDONESIAPT. Cipta KarsaMutiara Gas Development ProjectHandil – East KalimantanElectrical & InstrumentCK-22-
MCP/SPK/QQ/15/08/2013
107September 2013 – December 08, 2014PT. Toba Bara Sejahtera, Tbk.PT. Kutilang Paksi MasIPP PLTG SenipahSenipah – East KalimantanElectrical & Instrument012/KPM-KPU/PKS/X/2013September 30, 2013
108October 2013 – December 2013PT. Black Bear Resources
Indonesia
PT. Kutilang Paksi MasPemasangan Lampu Penerangan Tambahan dan Kalibrasi Peralatan InstrumentBontang – East KalimantanInstrumentB237/SPK-BBRI/X/2013October 03, 2013
109November 18, 2013 – December 12,
2013
PT. Kaltim Methanol IndustriRestroke Control Valve and Calibration of Transmitter For Turn Around 2013Bontang – East KalimantanElectrical & Instrument033/SPK-KMI/LOG/XI/2013November 06, 2013
110April 21, 2014 – December 20, 2014PT. Badak NGLDry Chemical at 24-D-6 (33-T-1452)
Improvement
Bontang – East KalimantanImprovement Fire EstinguisherCA-14002April 28, 2014
111June 11, 2014 – March 31, 2015Mobil Cepu LtdPT. Tripatra Engineers &
Constructor
Banyu Urip ProjectBojonegoro – East JawaElectrical9533-INWO-3240000545 Rev. 0June 11, 2014
112June 11, 2014 – October 31, 2014JOB Pertamina Talisman
Jambi Merang
PT. Suluh Ardhi EngineeringEPC Gas Metering At GrissikGrissik – South SumatraElectrical & InstrumentGRS-CT-N-003March 17, 2014
113July 2014 – October 2014VICOPT. Kaliraya SariVICO Compressor Pamaguan P-8Pamaguan – East KalimantanElectrical & InstrumentKRS-13-/SPK/OX/23/6/2014June 23, 2014
114September 02, 2014 – December 05,
2014
PT. Kaliraya SariManpower Supply for Water Injection Facility of Ampu Pressure, Maintenance ProjectEast KalimantanManpower SupplyBFK/SPK/AG/09/14/014 KRS-September 02, 2014
115September 1, 2014VICOPT. Kaliraya SariKalibrasi Gas LiftPamaguan – East KalimantanElectrical & Instrument
116September 2014 – October 2014PT. Toba Bara Sejahtera, Tbk.PT. Kutilang Paksi MasCommissioning 2 Unit GTG at PLTG
Senipah
Senipah – East KalimantanElectrical & Instrument
117October 01, 2014 – December 29, 2015PT. Pupuk Sriwidjaja
Palembang
PT. Toyo Engineering
Corporation
Pusri – II B ProjectPalembang – South SumateraElectrical & InstrumentBA-1066-AX-44-01December 24, 2013
118October 01, 2014 – October 30, 2015BP Berau Ltd.PT. Wijaya Karya (Persero)
Tbk
Tie-in Electrical Power & Instrument Untuk
Temporary Facility
West PapuaElectrical & InstrumentTP.02.01/NCDT.TGH/0292A /X/2014 Add.1September 29, 2015
119October 20, 2014 – December 03, 2014PT. Kaltim Methanol IndustriCalibration of Transmitter For Turn Around
2014
Bontang – East KalimantanCalibrationKMI/LOG/VIII/2014 025/SPK-August 26, 2014
120November 24, 2014 – December 29,
2014
PT. Kaltim Daya MandiriPulling Cable Trafo TursinaBontang – East KalimantanElectrical29/SPK/DIR/KDM/BTG/X/ 2014October 24, 2014
121December 01, 2014 – September 21,
2017
PT. Pupuk Kalimantan TimurPT. Inti Karya Persada Tehnik (IKPT)Kaltim 5 – Manpower dan Tools SupplyBontang – East KalimantanManpower dan Tools SupplyK5-00-C3-CT-034BNovember 27, 2014
122January 01, 2015 – December 31, 2015Mobil Cepu LtdPT. Tripatra Engineers &
Constructor
Banyu Urip ProjectBojonegoro – East JawaManpower Supply9533-ELWO-3240001070 Rev.2September 28, 2015
123July 24, 2015 – August 15, 2015PT. Pupuk Kalimantan TimurPekerjaan Perbaikan Instalasi Listrik
Conveyor System
Bontang – East KalimantanInstallation of Electrical Conveyor System298/SPPJ-BTG/2015July 1, 2015
124August 04, 2015 – October 31, 2017BP Berau Ltd.PT. Wijaya Karya (Persero)
Tbk
New Condensate & Diesel TanksBintuni – West PapuaElectrical & InstrumentTP.01.03/U.DEP.IP.NCDT- TGH/0855/III/2015March 25, 2015
125November 02, 2015 -June 30, 2016PT. Tropik Energi PandanPT. Sinergi Era CemerlangTropik Energi PandanLubuk Linggau – South SumatraElectrical & Instrument098/SEC-PO/X/2015October 07, 2015
126January 11, 2016 – May 06, 2017PT. Pupuk Sriwidjaja
Palembang
PT. Toyo Engineering
Corporation
Pusri – II B ProjectPalembang – South SumateraManpower SupplyBA-1066-AX-82-01January 08, 2016
127February 08, 2016 – February 09, 2017ConocoPhilips IndonesiaPT. Inti Karya Persada
Tehnik (IKPT)
Dayung Compression Phase-2 (DC-2
Project)
Dayung – South SumatraElectrical & InstrumentDC2-CNT-CON-004-EFebruary 15, 2016
128February 08, 2016 – March 06, 2016PT. Kaltim Parna IndustriCalibration Transmitter, Control Valve, &
Switch All Area
Bontang – East KalimantanCalibrasi Transmitter, Control Valve, & Switch055/KPI/CA/I/2016 (19514)February 08, 2016
129March 21, 2016 – April 30, 2017PT. PertaminaPT. Wijaya Karya (Persero)
Tbk
Pengembangan Terminal BBM Pulau SambuBatamElectrical & InstrumentTP.01.03/U.DEP.IP.P.SAMBU /0461/III/2016March 21, 2016
130July 21, 2016 – April 18, 2017ConocoPhilips IndonesiaPT. Shaftindo EnergiSuban #15 ProjectSuban – South SumateraElectrical & InstrumentLOG/16/1622July 19, 2016
131December 05, 2016 – January 31, 2017ConocoPhilips IndonesiaPT. Shaftindo EnergiSuban LaydownSuban – South SumateraElectrical & InstrumentSO/16/0056November 29, 2016
132November 15, 2016 – October 05, 2018PT. Synthetic Rubber
Indonesia
PT. Inti Karya Persada
Tehnik
120 KTA Synthetic Rubber – U3 ProjectCilegon – BantenInstrumentAY4501November 29, 2016
133February 13, 2017 – December 04, 2017Millenium Challenge Account –
Indonesia (MCA-Indonesia)
PT. Inti Karya Persada
Tehnik
Solar Photovoltaic Electricity for
Karampuang Island Project
Mamuju – West SulawesiElectrical, Instrument, & Civil Building WorksAW-4401February 10, 2017
134July 11, 2017 – April 28, 2018Millenium Challenge Account –
Indonesia (MCA-Indonesia)
PT. Inti Karya Persada
Tehnik
Solar Photovoltaic Electricity for Tomia
Project
Wakatobi – Southeast SulawesiElectrical, Instrument, & Civil WorksWKB-IKPT-SC-LOI-001July 05, 2017
135August 2017 – September 2017PT. Pupuk Kalimantan TimurPT. Siemens IndonesiaUpgrade Control System Quadrant Arm
Loader
Bontang – East KalimantanElectrical4507471980May 02, 2017
136August 2017 – August 29, 2017PT. Kaltim Parna IndustriKalibrasi Transmitter, Switch & Control
Valve
Bontang – East KalimantanCalibration137/26152/KPI- SPK/VII/2017July 24, 2017
135September 07, 2017 – October 07, 2017PT. Badak NGLPT. ABB Sakti IndustriSite Installation WorkBontang – East KalimantanSite Support3762006509July 20, 2017
136October 08, 2017 – October 21, 2017PT. Badak NGLPT. ABB Sakti IndustriAdditional MandaysBontang – East KalimantanSite Support3762006915December 19, 2017
137December 15, 2017 – August 13, 2018PT. Oki Pulp & Paper MillsPT. Timas SuplindoOki – Tissue Machine ProjectOgan Komering Ilir – South
Sumatera
Electrical, Instrument, &
Automation
217/TMS-HO/PKS
LI/XII/2017
December 15, 2017
136March 27, 2018 – May 15, 2018PT. Oki Pulp & Paper MillsPT. Timas SuplindoOki – Tissue Machine ProjectOgan Komering Ilir – South
Sumatera
Electrical, Instrument, &
Automation
036/TMS-HO/PKS
LI/III/2017
March 04, 2018
137April 25, 2018 – May 25, 2018PT. Oki Pulp & Paper MillsPT. Timas SuplindoOki – Tissue Machine ProjectOgan Komering Ilir – South
Sumatera
Jasa Penarikan Kabel PowerTSON/PO/1804-02768April 25, 2018
138October 1, 2018PT. Oki Pulp & Paper MillsPT. Timas SuplindoOki – Tissue Machine ProjectOgan Komering Ilir – South
Sumatera
Manpower Acceleration
Tahap 1
TSON/PO/1810-05670October 02, 2018
139December 15, 2017 – September 07,
2018
PT. Industri Nabati LestariPT. Wijaya Karya (Persero) TbkProyek Pembangunan Pabrik Minyak Goreng 600.000 TPYSei Mangkei, Simalungun – North SumateraElectrical & InstrumentTP.01.01/U.DEP.IP.D.PMG/2 543/XII/2017December 15, 2017
140March 01, 2018 – March 22, 2018PT. Chandra Asri
Petrochemical Tbk
PT. Inti Karya Persada
Tehnik
NPE Project 400 KTA New Swing Plant of
HDPE, LLDPE and mLLDPE
Cilegon – BantenTie-In InstrumentNPE-WO-AX-4502January 31, 2018
141March 20, 2018 – March 22, 2018PT. Chandra Asri
Petrochemical Tbk
PT. Inti Karya Persada
Tehnik
NPE Project 400 KTA New Swing Plant of
HDPE, LLDPE and mLLDPE
Cilegon – BantenSupport VSM Yokogawa for Tie-In InstrumentNPE-CPL-CNT-AX-4504March 20, 2018
142April 19, 2018 – June 30, 2018PT. Chandra Asri
Petrochemical Tbk
PT. Artha Teknik AbadiNPE ProjectCilegon – BantenCathodic Protection Work286/PO/ATA/IV/18/Rev.02April 17, 2018
143May 16, 2018 – October 15, 2018PT. Synthetic Rubber
Indonesia
PT. Inti Karya Persada
Tehnik
120 KTA Synthetic Rubber – U3 ProjectCilegon – BantenSupply ManpowerAY4821May 15, 2018
144May 31, 2018 – July 31, 2018PT. Riau Andalan Pulp &
Paper
PT. Timas SuplindoCS2 Recovery & SpinbathKerinci – RiauElectrical083/TMS-HO/PKS- LI/VI/2018May 31, 2018
145June 25, 2018 – July 31, 2019PT. Chandra Asri
Petrochemical Tbk
PT. Inti Karya Persada
Tehnik
400 KTA New Swing Plant HDPE, LLDPE,
and mLLDPE
Cilegon – BantenElectricalNPE-CPL-LOI-AX-4401May 10, 2018
146July 2018 – March 2019PT. PLN (Persero)PT. Satyamitra Surya PerkasaPLTU Lontar ProjectLontar – TangerangInstallation Cable Tray,
Lighting & Instrument
100033283July 11, 2018
147July 23, 2018 – December 31, 2018BP Berau Ltd.CSTS JO (PT. Tripatra
Engineers & Constructors,
PT. Chiyoda International
Indonesia, PT. Saipem
Indonesia, PT. Suluh Ardhi
Engineering)
LAN, PA/GA, CCTV Installation for
Tangguh Onshore Expansion EPC Project
Bintuni – West PapuaInstallation, Testing & Commissioning1235823August 10, 2018
148October 16, 2018 – December 20, 2018PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk
EPCC Pengembangan & Modernisasi PG
Assembagoes Situbondo
Situbondo – East JavaElectricalASSEMBAGOES/086/X/2018 TP.02.01/U.DEP.IP.PGAugust 16, 2018
149October 18, 2018 – December 20, 2018PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk
EPCC Pengembangan & Modernisasi PG
Assembagoes Situbondo
Situbondo – East JavaElectricalASSEMBAGOES/089/X/2018 TP.02.01/U.DEP.IP.PGAugust 18, 2018
150October 20, 2018 – December 20, 2018PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk
EPCC Pengembangan & Modernisasi PG
Assembagoes Situbondo
Situbondo – East JavaElectricalASSEMBAGOES/091/X/2018 TP.02.01/U.DEP.IP.PGAugust 18, 2018
151October 15, 2018 – February 26, 2019PT. Pindo Deli 3PT. Timas SuplindoPindo Deli Karawang ProjectKarawang – West JavaElectrical & InstrumentationTSON/PO/1810-05742October 05, 2018
152November 1, 2018PT. PLN (Persero)PT. Satyamitra Surya PerkasaPLTU Lontar ProjectLontar – TangerangKalibrasi Alat Pressure
Gauge with Switch
100039098November 22, 2018
153November 19, 2018 – February 14, 2019PT. Pupuk Kalimantan TimurPT. Inti Karya Persada
Tehnik
Kaltim-5 Project (Shutdown Activity 2018)Bontang – East KalimantanElectrical & InstrumentationAX-4401November 19, 2018
153January 23, 2019 – June 30, 2019PT. Pupuk Sriwidjaja
Palembang
PT. Wijaya Karya (Persero)
Tbk
Proyek Pembangunan Pabrik NPK Fusion II
Kapasitas 2×100.000 MTPY PT. Pupuk
Sriwidjaja
Palembang – South SumateraElectrical & InstrumentationTP.01.03/U.DEP.IP.NPKII/18
9/I/2019
January 23, 2019
153February 01, 2019 – January 31, 2020BP Berau Ltd.CSTS JO (PT. Tripatra
Engineers & Constructors,
PT. Chiyoda International
Indonesia, PT. Saipem
Indonesia, PT. Suluh Ardhi
Engineering)
Supply of Construction Manpower Onshore
LNG EPC for Tangguh Expansion Project
Bintuni – West PapuaSupply Manpower5000036918January 30, 2019
154March 01, 2019 – September 01, 2019PT. PLN (Persero)PT. Satyamitra Surya PerkasaPLTU Lontar ProjectLontar – TangerangPulling Cable &
Termination
100042989March 01, 2019
155March 11, 2019 – May 11, 2019PT. Perkebunan Nusantara
XI
PT. Wijaya Karya (Persero)
Tbk dan
Jasa Instalasi Elektrikal & Instrument untuk
Area Boiler Package
Kudus – Central JawaElectrical & Instrumentation066/SPK/III/BMSC/2019March 06, 2019